Welcome to the November edition of our project newsletter.
In this issue, we share the latest project progress and key milestones achieved over recent months. Thank you for your continued interest and support as the project moves forward.
Upcoming Community Engagement Events
Our next community engagement session will take place with the Friendship Group at Abergavenny Methodist Church on Thursday 26 November at 2.00pm.
As the project moves into its winter phase, this 30-minute session will provide residents with an update on site demobilisation, access arrangements, fencing and other planned activities. It will also explain why there may be less visible activity on site over the winter months.

Piling Works Completed
Another important stage of the project has been completed, with all piling works for the north and south bridge abutments now finished. In total, six piles have been installed, three at each abutment, using the Continuous Flight Auger (CFA) method previously featured in our newsletters.
Like the caisson, much of this work will eventually be hidden beneath the completed bridge, but it plays a vital role in supporting the new structure. The piles provide the strong foundations needed for the abutments at either end of the bridge. Together with the completion of the caisson, the finished piling works mark significant progress in establishing the bridge foundations and another important step forward for the project.
Next steps…
Following the successful completion of the caisson and piling works, the project will now move into the next phase of construction, with formwork and reinforced concrete works (FRC) commencing to the bridge abutments and caisson.
This next stage will involve installing steel reinforcement and constructing formwork, which acts as a temporary mould into which concrete is poured to create the required shape of the permanent structures.
For the remainder of 2026, works will focus on constructing the initial base sections of the north and south abutments, together with the first section of the caisson capping slab.
As we approach the end of the permitted river working window and the project’s planned demobilisation period, these works will bring this year’s programme of major foundation construction to a close, post reinstatement. The remaining sections of the abutments and associated concrete structures will then continue as part of the 2027 construction programme
‘Llanfoist Links’ – Additional plans announced
Whilst on-site construction of the active travel bridge pauses over winter, two other important pieces of work will get underway: Firstly, the bridge fabrication will begin off-site, and secondly, works to the highway are planned to create improved links to the new bridge on the Llanfoist side.
The highway improvements will help make everyday journeys easier for people travelling to Abergavenny town centre, Castle Meadows, local shops, schools, work and nearby communities without needing to rely on a car. The design will address long-standing issues along Merthyr Road, south of Usk Bridge, including narrow sections of footway, limited crossing points and no provision for cycling.
Construction of the additional links is planned for winter 2026 to spring 2027. The plans for this construction scheme have been developed through public and stakeholder consultation, and will include crossing upgrades and realignment of the highway to accommodate a shared use path on the route between the new walking and cycling bridge and the underpass to The Cutting.
For more information on the planned works and to view details of the plan, please visit the ‘Llanfoist Links’ section of the MCC website: www.monmouthshire.gov.uk/highways/active-travel/active-travel-in-abergavenny-and-llanfoist/
Visit the MCC website to see the design in detail
Social Value and Community Engagement
The Llanfoist to Abergavenny Active Travel Bridge and Links scheme continues to make a positive contribution to the local community through a range of social value initiatives.
Balfour Beatty held a community engagement event at Abergavenny Methodist Hall in early October (see the top of this newsletter for the next drop-in on November 26th) and provided a display about the bridge construction works to MCC Active Travel for their information station at the Greener Abergavenny Fair on October 18th.
Councillor Sara Burch, Monmouthshire County Council Cabinet Member for Rural Affairs, Housing & Tourism said:
“It was great to see so many people attend the drop-in. The Balfour Beatty team were able to explain the engineering works that were happening to construct the base for the bridge, and how they are safeguarding the biodiversity of the river and meadows. I think the whole town is now looking forward to seeing the project completed.”