Upcoming Community Engagement Events

Our next community engagement session will take place with the Friendship Group at Abergavenny Methodist Church on Thursday 26 November at 2.00pm.

As the project moves into its winter phase, this 30-minute session will provide residents with an update on site demobilisation, access arrangements, fencing and other planned activities. It will also explain why there may be less visible activity on site over the winter months.

Site demobilisation will begin in November 2026, with heavy lifting equipment stopping operations and being
removed from site. The site cabins are also currently expected to be removed over the winter. Some Heras fencing will remain around the site compound and abutment areas, while fencing that is no longer required will be removed as part of the demobilisation works.

Construction access tracks have been laid on Castle Meadows to allow heavy plant access to the working site from the road. During the winter, the construction access tracks will be cleared away, and the topsoil will be re-laid and covered with Jute Soil Saver matting. The roots of plants normally help prevent topsoil from being washed away by flood water. Seeding is unsuitable at this time of year, so the matting is needed to protect the valuable topsoil against flooding erosion.
The matting will cover a total area of 850m2 and will be held down using timber pegs. To reduce the trip hazard, the matting and pegs will be driven close to the ground. However, we’d encourage people to take care around it, stay off the matting, and use the paths provided. The Public Right of Way diversion paths will remain in place.
Throughout the winter period, access will be maintained for cattle to reach their designated safe area in the event of flooding, as agreed with the farmer and relevant stakeholders.
To find out more or register your interest, please email aats@balfourbeatty.com.

Construction Update | October Progress

Caisson Construction Completed
Another significant milestone has been reached with the successful completion of the caisson, an important part of the foundations that will support the new bridge.
Following the installation of the steel reinforcement cage, the concrete pour has been completed, forming the
permanent caisson structure. This was a key stage of the works and required careful planning and coordination by the project team.
With the caisson now in place, work can progress to the next stages of the bridge construction, marking another important step forward for the project.

Piling Works Completed
Another important stage of the project has been completed, with all piling works for the north and south bridge abutments now finished. In total, six piles have been installed, three at each abutment, using the Continuous Flight Auger (CFA) method previously featured in our newsletters.

Like the caisson, much of this work will eventually be hidden beneath the completed bridge, but it plays a vital role in supporting the new structure. The piles provide the strong foundations needed for the abutments at either end of the bridge. Together with the completion of the caisson, the finished piling works mark significant progress in establishing the bridge foundations and another important step forward for the project.

Next steps…
Following the successful completion of the caisson and piling works, the project will now move into the next phase of construction, with formwork and reinforced concrete works (FRC) commencing to the bridge abutments and caisson.

This next stage will involve installing steel reinforcement and constructing formwork, which acts as a temporary mould into which concrete is poured to create the required shape of the permanent structures.

For the remainder of 2026, works will focus on constructing the initial base sections of the north and south abutments, together with the first section of the caisson capping slab.

As we approach the end of the permitted river working window and the project’s planned demobilisation period, these works will bring this year’s programme of major foundation construction to a close, post reinstatement. The remaining sections of the abutments and associated concrete structures will then continue as part of the 2027 construction programme

‘Llanfoist Links’ – Additional plans announced 
Whilst on-site construction of the active travel bridge pauses over winter, two other important pieces of work will get underway: Firstly, the bridge fabrication will begin off-site, and secondly, works to the highway are planned to create improved links to the new bridge on the Llanfoist side.

The highway improvements will help make everyday journeys easier for people travelling to Abergavenny town centre, Castle Meadows, local shops, schools, work and nearby communities without needing to rely on a car. The design will address long-standing issues along Merthyr Road, south of Usk Bridge, including narrow sections of footway, limited crossing points and no provision for cycling.

Construction of the additional links is planned for winter 2026 to spring 2027. The plans for this construction scheme have been developed through public and stakeholder consultation, and will include crossing upgrades and realignment of the highway to accommodate a shared use path on the route between the new walking and cycling bridge and the underpass to The Cutting.

For more information on the planned works and to view details of the plan, please visit the ‘Llanfoist Links’ section of the MCC website: www.monmouthshire.gov.uk/highways/active-travel/active-travel-in-abergavenny-and-llanfoist/

Visit the MCC website to see the design in detail

Social Value and Community Engagement
The Llanfoist to Abergavenny Active Travel Bridge and Links scheme continues to make a positive contribution to the local community through a range of social value initiatives.

Balfour Beatty held a community engagement event at Abergavenny Methodist Hall in early October (see the top of this newsletter for the next drop-in on November 26th) and provided a display about the bridge construction works to MCC Active Travel for their information station at the Greener Abergavenny Fair on October 18th.

Councillor Sara Burch, Monmouthshire County Council Cabinet Member for Rural Affairs, Housing & Tourism said:
“It was great to see so many people attend the drop-in. The Balfour Beatty team were able to explain the engineering works that were happening to construct the base for the bridge, and how they are safeguarding the biodiversity of the river and meadows. I think the whole town is now looking forward to seeing the project completed.”


Contact us

If you’ve got a question about the project, you can email the team via: aats@balfourbeatty.com

Alternatively, you can contact our project manager, Ryan Anderson, on 07580 982399.

Out of hours and urgent?

Please contact our out of hours helpline on 0800 121 4444 or email: help@balfourbeatty.com 

Sign up to receive this newsletter direct

If you would like to sign up to receive a copy of the newsletter via email, please visit our website by scanning the QR code below.

This newsletter is available in other formats on request.